May 16, 2025

Olde Park Place

  • Landscape ongoing
  • Brick pavers being installed.

Aikens between 2nd and Eagle

  • Placing silva cells
  • Placing ¾” aggregate for road base.
  • Electrical work ongoing.
  • Curb and sidewalk ongoing.

Olde Park To Eagle Rd

  • Road closure anticipated May 5th – May 30th.
  • Veolia installing water – Night work starting May 14th.
  • Silva cells ongoing.
  • Prepping and placing sidewalk crossings.


Share May 16, 2025 on Facebook Share May 16, 2025 on Twitter Share May 16, 2025 on Linkedin Email May 16, 2025 link

This project is substantially complete. 