May 22, 2025 - Construction Update

22 May 2025

Olde Park

  • Landscape ongoing
  • Brick paver installation

Aikens between 2nd and Eagle

  • Placing silva cells
  • Placing ¾” aggregate for road base
  • Electrical work ongoing
  • Curb and sidewalk ongoing
  • Paving anticipated the week of May 26th

Olde Park To Eagle Rd

  • Road closure anticipated May 5th – May 30th
  • Veolia installing water – Night work starting May 14th
  • Silva cells ongoing
  • Prepping and placing sidewalk crossings
  • Paving anticipated the week of May 26t

Eagle Rd Closure - Starting approximately June 4th - Veolia placing utilities. Sidewalk work.