May 22, 2025 - Construction Update
Olde Park
- Landscape ongoing
- Brick paver installation
Aikens between 2nd and Eagle
- Placing silva cells
- Placing ¾” aggregate for road base
- Electrical work ongoing
- Curb and sidewalk ongoing
- Paving anticipated the week of May 26th
Olde Park To Eagle Rd
- Road closure anticipated May 5th – May 30th
- Veolia installing water – Night work starting May 14th
- Silva cells ongoing
- Prepping and placing sidewalk crossings
- Paving anticipated the week of May 26t
Eagle Rd Closure - Starting approximately June 4th - Veolia placing utilities. Sidewalk work.