May 23, 2024
- Stage 1 - Eagle Road between Plaza and Aikens
- 4-Way Stop at Eagle & Plaza.
- Bottom lift paving between Plaza & Aikens complete.
- Veolia will need to shut down Aikens for water change over.
- Stage 2 - Front of Albertsons - East side of Eagle between Highway 44 and Plaza.
- Utilities relocating.
- Concrete ongoing.
- Will be working on Plaza side.