May 30, 2025
Olde Park
- Landscape ongoing.
- Brick paver installation.
Aikens between 2nd and Eagle
- Placing silva cells.
- Placing ¾” aggregate for road base.
- Electrical work ongoing.
- Curb and sidewalk ongoing.
- Asphalt paving was done May 29th. Road to be opened June 6th after striping and manhole collaring is complete.
Olde Park To Eagle Rd
- Road closure anticipated May 5th – June 6th
- Veolia installing water – Night work starting May 14th.
- Silva cells ongoing.
- Prepping and placing sidewalk crossings.
- Paving scheduled for May 30th.
Starting June 6th, Eagle Road will be closed between Plaza and Old State. Veolia is installing a water line. Excavation and storm drain installation.