May 30, 2025

30 May 2025

Olde Park

  • Landscape ongoing.
  • Brick paver installation.

Aikens between 2nd and Eagle

  • Placing silva cells.
  • Placing ¾” aggregate for road base.
  • Electrical work ongoing.
  • Curb and sidewalk ongoing.
  • Asphalt paving was done May 29th. Road to be opened June 6th after striping and manhole collaring is complete.

Olde Park To Eagle Rd

  • Road closure anticipated May 5th – June 6th
  • Veolia installing water – Night work starting May 14th.
  • Silva cells ongoing.
  • Prepping and placing sidewalk crossings.
  • Paving scheduled for May 30th.

Starting June 6th, Eagle Road will be closed between Plaza and Old State. Veolia is installing a water line. Excavation and storm drain installation.


Share May 30, 2025 on Facebook Share May 30, 2025 on Twitter Share May 30, 2025 on Linkedin Email May 30, 2025 link
#<Object:0x0000000022d025d8>