May 30, 2025

Olde Park

  • Landscape ongoing.
  • Brick paver installation.

Aikens between 2nd and Eagle

  • Placing silva cells.
  • Placing ¾” aggregate for road base.
  • Electrical work ongoing.
  • Curb and sidewalk ongoing.
  • Asphalt paving was done May 29th. Road to be opened June 6th after striping and manhole collaring is complete.

Olde Park To Eagle Rd

  • Road closure anticipated May 5th – June 6th
  • Veolia installing water – Night work starting May 14th.
  • Silva cells ongoing.
  • Prepping and placing sidewalk crossings.
  • Paving scheduled for May 30th.

Starting June 6th, Eagle Road will be closed between Plaza and Old State. Veolia is installing a water line. Excavation and storm drain installation.


Share May 30, 2025 on Facebook Share May 30, 2025 on Twitter Share May 30, 2025 on Linkedin Email May 30, 2025 link

This project is substantially complete. 

#<Object:0x00007f6e33a54dc8>