May 8, 2025

08 May 2025

Olde Park Place

  • Landscape ongoing.
  • Brick pavers installation.

Aikens between 2nd and Eagle

  • Placing silva cells.
  • Placing ¾” aggregate for road base.
  • Electrical work ongoing.
  • Curb anticipated week of May 5th.

Olde Park to Eagle Rd

  • Road closure anticipated May 5th – end of May.
  • Veolia installing water.
  • Silva cells ongoing.
  • Prepping and placing sidewalk crossings.