November 7, 2024

Eagle Road in front of Albertsons

  • Idaho Power poles relocated.
  • Once 2nd street is open, moving back to finish Eagle Rd.

2nd Street and State Street

  • State Street open heading east and west.
  • Silva Cells installed.
  • Signal installed.
  • Curb and sidewalk ongoing.
  • 2nd Street crosswalk being placed.
Share November 7, 2024 on Facebook Share November 7, 2024 on Twitter Share November 7, 2024 on Linkedin Email November 7, 2024 link

This project is substantially complete. 