November 7, 2024
Eagle Road in front of Albertsons
- Idaho Power poles relocated.
- Once 2nd street is open, moving back to finish Eagle Rd.
2nd Street and State Street
- State Street open heading east and west.
- Silva Cells installed.
- Signal installed.
- Curb and sidewalk ongoing.
- 2nd Street crosswalk being placed.