October 10, 2024
Eagle Road in front of Albertsons
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.
2nd Street and State Street
- 2nd and State intersection closed.
- Silva cells being installed.
- Light pole bases, conduit and signal work ongoing.
- Curb and sidewalk being prepped.
- Curb and sidewalk being placed October 10th – October 22nd.
- Asphalt paving anticipated October 24th.