October 10, 2025

Aikens between 2nd and Eagle

  • Landscaping is ongoing. Water tie-in is required for basin.

Eagle Rd & State Intersection

  • Signal turned on September 11th

.State Street, Eagle to 2nd Street

  • Road closed starting September 2nd
  • Curb placed on south side
  • Brick Pavers ongoing on side
  • Sidewalk started on north side
  • Silva Cells being installed
  • Weather permitting – Paving October 10th
  • Colored concrete crosswalks will be installed after pavement
Share October 10, 2025 on Facebook Share October 10, 2025 on Twitter Share October 10, 2025 on Linkedin Email October 10, 2025 link

This project is substantially complete. 