Aikens between 2nd and Eagle

  • Landscaping is ongoing. Water tie-in is required for basin.

Eagle Rd & State Intersection

  • Signal turned on September 11th

.State Street, Eagle to 2nd Street

  • Road closed starting September 2nd
  • Curb placed on south side
  • Brick Pavers ongoing on side
  • Sidewalk started on north side
  • Silva Cells being installed
  • Weather permitting – Paving October 10th
  • Colored concrete crosswalks will be installed after pavement
Share October 10, 2025 on Facebook Share October 10, 2025 on X (formerly Twitter) Share October 10, 2025 on Linkedin Email October 10, 2025 link

This project is substantially complete. 