Eagle Road in front of Albertsons
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st
2nd Street and State Street
- 2nd and State intersection closed
- Silva Cells installed
- Light pole bases, conduit and signal work ongoing
- Curb and sidewalk being prepped
- Curb and sidewalk being placed October 10th – October 22nd
- Asphalt paving anticipated October 24th
Share October 17, 2024 on Facebook
Share October 17, 2024 on X (formerly Twitter)
Share October 17, 2024 on Linkedin
Email October 17, 2024 link
This project is substantially complete.