October 17, 2024

17 Oct 2024

Eagle Road in front of Albertsons

  • Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st

2nd Street and State Street

  • 2nd and State intersection closed
  • Silva Cells installed
  • Light pole bases, conduit and signal work ongoing
  • Curb and sidewalk being prepped
  • Curb and sidewalk being placed October 10th – October 22nd
  • Asphalt paving anticipated October 24th