October 17, 2025
Aikens between 2nd and Eagle
Landscaping is ongoing. Water tie-in is required for basin. Tie in Anticipated starting week of Oct 20th once State St. is open.
State Street, Eagle to 2nd Street
Brick Pavers ongoing on both sides. Sidewalk started on north side. Silva Cells being installed. Paving complete. Colored concrete crosswalks being installed.
Share October 17, 2025 on Facebook
Share October 17, 2025 on Twitter
Share October 17, 2025 on Linkedin
Email October 17, 2025 link
This project is substantially complete.