October 2, 2025

Aikens between 2nd and Eagle

  • Landscaping ongoing.
  • Water tie in required for basin.

Eagle Rd & State Intersection

  • Signal turn on Sept 11th.

State Street, Eagle to 2nd St - Road closed starting September 2nd. Curb placed on south side. Brick Pavers ongoing on side. Sidewalk started on North side. Silva Cells being installed.


Share October 2, 2025 on Facebook Share October 2, 2025 on Twitter Share October 2, 2025 on Linkedin Email October 2, 2025 link

This project is substantially complete. 