October 24, 2025

Aikens between 2nd and Eagle

  • Landscaping is ongoing. Water tie-in is required for basin.
  • Water tie in started October 22nd with an anticipated time frame of 4 days.

State Street, Eagle to 2nd Street

  • Brick pavers ongoing on both sides.
  • Asphalt paving complete.
  • Colored concrete installed

State and 2nd Intersection

  • Replacing crosswalk with concrete.
  • After 2nd Street is complete.