October 24, 2025

Aikens between 2nd and Eagle

  • Landscaping is ongoing. Water tie-in is required for basin.
  • Water tie in started October 22nd with an anticipated time frame of 4 days.

State Street, Eagle to 2nd Street

  • Brick pavers ongoing on both sides.
  • Asphalt paving complete.
  • Colored concrete installed

State and 2nd Intersection

  • Replacing crosswalk with concrete.
  • After 2nd Street is complete.


Share October 24, 2025 on Facebook Share October 24, 2025 on Twitter Share October 24, 2025 on Linkedin Email October 24, 2025 link

This project is substantially complete. 