October 4, 2024

Eagle Road in front of Albertsons

  • Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.

2nd Street and State Street

  • 2nd and State intersection closed starting September 25th.
  • Signal pole bases being placed.
  • Concrete removed on North side.
  • Storm drain complete.
  • Silva Cells being installed.
  • Light pole bases, conduit and signal work ongoing.
  • Curb and sidewalk being prepped.
Share October 4, 2024 on Facebook Share October 4, 2024 on Twitter Share October 4, 2024 on Linkedin Email October 4, 2024 link

This project is substantially complete. 

#<Object:0x00000000384025d0>