October 4, 2024
Eagle Road in front of Albertsons
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.
2nd Street and State Street
- 2nd and State intersection closed starting September 25th.
- Signal pole bases being placed.
- Concrete removed on North side.
- Storm drain complete.
- Silva Cells being installed.
- Light pole bases, conduit and signal work ongoing.
- Curb and sidewalk being prepped.