Eagle Road in front of Albertsons

  • Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.

2nd Street and State Street

  • 2nd and State intersection closed starting September 25th.
  • Signal pole bases being placed.
  • Concrete removed on North side.
  • Storm drain complete.
  • Silva Cells being installed.
  • Light pole bases, conduit and signal work ongoing.
  • Curb and sidewalk being prepped.