Olde Park

  • Landscape and brick pavers ongoing.

Aikens between 2nd and Eagle

  • Landscaping ongoing.
  • Water tie in required for basin.

Eagle Rd & State Intersection

  • Signal turn on Sept 11th.

State Street, Eagle to 2nd St

  • Road closed starting September 2nd.
  • Curb being placed on south side.
  • Sidewalk ongoing between Eagle and 1st Street.
  • Removal of sidewalk on south side ongoing.
  • Underground electrical ongoing.


Share September 12, 2025 on Facebook Share September 12, 2025 on X (formerly Twitter) Share September 12, 2025 on Linkedin Email September 12, 2025 link

This project is substantially complete. 