September 13, 2024
Eagle Road in front of Albertsons
- Pavement markings remaining.
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of Sept 30th.
2nd Street and State Street
- Started September 3rd.
- Underground work first - Veolia ongoing.
- Signal pole bases being placed.
- One way traffic on State St. - East bound only traffic.
- Century Link lowering utilities.