September 20, 2024
Eagle Road in front of Albertsons
- Pavement markings remaining.
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.
2nd Street and State Street
- Started September 3rd - Underground work first. Veolia ongoing.
- Signal pole bases being placed.
- One way traffic on State St. - East bound only first stage.
- Century Link lowering facilities.