September 20, 2024

Eagle Road in front of Albertsons

  • Pavement markings remaining.
  • Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.


2nd Street and State Street

  • Started September 3rd - Underground work first. Veolia ongoing.
  • Signal pole bases being placed.
  • One way traffic on State St. - East bound only first stage.
  • Century Link lowering facilities.