September 26, 2024

Eagle Road in front of Albertsons

  • Pavement markings remaining.
  • Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.

2nd Street and State Street

  • 2nd and State intersection closed starting September 25th.
  • Signal pole bases being placed.
  • Concrete removed on north side.
  • Storm drain and Veola water work ongoing.
  • Historic lights being removed September 30th.
  • Electrical conduit being placed afterwards.


Share September 26, 2024 on Facebook Share September 26, 2024 on Twitter Share September 26, 2024 on Linkedin Email September 26, 2024 link

This project is substantially complete. 