September 26, 2024

Eagle Road in front of Albertsons

  • Pavement markings remaining.
  • Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.

2nd Street and State Street

  • 2nd and State intersection closed starting September 25th.
  • Signal pole bases being placed.
  • Concrete removed on north side.
  • Storm drain and Veola water work ongoing.
  • Historic lights being removed September 30th.
  • Electrical conduit being placed afterwards.


Share September 26, 2024 on Facebook Share September 26, 2024 on Twitter Share September 26, 2024 on Linkedin Email September 26, 2024 link