September 26, 2024
Eagle Road in front of Albertsons
- Pavement markings remaining.
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.
2nd Street and State Street
- 2nd and State intersection closed starting September 25th.
- Signal pole bases being placed.
- Concrete removed on north side.
- Storm drain and Veola water work ongoing.
- Historic lights being removed September 30th.
- Electrical conduit being placed afterwards.