September 26, 2025

Aikens between 2nd and Eagle

  • Landscaping ongoing
  • Water tie in required for basin

Eagle Rd & State Intersection

  • Signal turn on Sept 11th

State Street, Eagle to 2nd St

  • Road closed starting September 2nd
  • Curb being placed on south side
  • Sidewalk ongoing between Eagle and 1st Street
  • Underground electrical ongoing
  • Silva Cells being installed
Share September 26, 2025 on Facebook Share September 26, 2025 on Twitter Share September 26, 2025 on Linkedin Email September 26, 2025 link

This project is substantially complete. 