September 26, 2025

Aikens between 2nd and Eagle

  • Landscaping ongoing
  • Water tie in required for basin

Eagle Rd & State Intersection

  • Signal turn on Sept 11th

State Street, Eagle to 2nd St

  • Road closed starting September 2nd
  • Curb being placed on south side
  • Sidewalk ongoing between Eagle and 1st Street
  • Underground electrical ongoing
  • Silva Cells being installed
Share September 26, 2025 on Facebook Share September 26, 2025 on X (formerly Twitter) Share September 26, 2025 on Linkedin Email September 26, 2025 link

This project is substantially complete. 