September 5, 2025
Olde Park
- Landscape and brick pavers ongoing
Aikens between 2nd and Eagle
- Landscaping ongoing
- Water tie in required for basin
Eagle Rd & State Intersection
- Signal Poles being placed - turn on September 10th.
- Temporary Stop Signs in place.
State Street, Eagle to 2nd St
- Road closed starting September 2nd.
- Curb being placed on south side.
- Sidewalk ongoing between Eagle and 1st Street.
- Removal of sidewalk on south side ongoing.
Share September 5, 2025 on Facebook
Share September 5, 2025 on X (formerly Twitter)
Share September 5, 2025 on Linkedin
Email September 5, 2025 link
This project is substantially complete.