September 6, 2024

Front of Albertsons

  • Pavement markings remaining.
  • Waiting on Idaho Power to relocate power poles.


2nd Street and State Street

  • Work started September 3rd.
  • Underground work is being done first - Veolia working nights.
  • Signal pole bases being placed.
  • One way traffic on State St. East bound only.
Share September 6, 2024 on Facebook Share September 6, 2024 on X (formerly Twitter) Share September 6, 2024 on Linkedin Email September 6, 2024 link

This project is substantially complete. 