Downtown Eagle Mobility Improvements: Eagle Road and State Street

Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Facebook Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Twitter Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Linkedin Email Downtown Eagle Mobility Improvements: Eagle Road and State Street link

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

*Phase 1 of the project is expected to be complete by Fall 2024

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

*Phase 1 of the project is expected to be complete by Fall 2024

  • February 9, 2024

    Share February 9, 2024 on Facebook Share February 9, 2024 on Twitter Share February 9, 2024 on Linkedin Email February 9, 2024 link
    • The anticipated start date is February 12th. NE Corner of Plaza and Eagle.
    • Work will begin on the east side of Eagle between Plaza and Aikens, with the northbound lane being restricted and moved into the center lane.
    • One lane of travel will remain open in each direction, and business access will be maintained. Signs will be in place to alert drivers of the new traffic pattern.


  • Construction to start in early February

    Share Construction to start in early February on Facebook Share Construction to start in early February on Twitter Share Construction to start in early February on Linkedin Email Construction to start in early February link

    Construction will begin early February, along with significant water and power utility work. Phase 1 work is expected to be complete by Fall 2024. Phase 2 will follow and is scheduled for completion Fall 2025.

    Phase 1 includes work on the following three road sections:

    • Eagle Road, SH-44 to the canal (just north of Plaza Drive)
    • Plaza Drive, Eagle Road to 2nd Street
    • State Street and 2nd Street intersection

    Access to businesses will remain open at all times. Ingress and egress may be shifted to accommodate construction. If business access will be impacted, the contractor will coordinate with the businesses.

    Work will include, but is not limited to:

    • Temporary closures
    • Lane restrictions
    • Temporary on-street parking restrictions
    • Typical construction noise
    • Dust
    • Equipment backup alarms
    • Ground vibration
    • Veolia water line and other utility work

    Work is anticipated to occur between 7:00 a.m. and 7:00 p.m. Some night and weekend work is expected.

    *Construction schedules are subject to change.

    Learn More!

    Construction Open House

    • January 31, 2024 | 3:00 p.m. to 7:00 p.m.
    • Hilton Garden Inn | 145 E. Riverside Dr., Eagle, ID
    • Visit anytime between 3:00 and 7:00 p.m. Please note this is an informal open house, with no formal presentation.
    • Materials from open house
  • January 12, 2024

    Share January 12, 2024 on Facebook Share January 12, 2024 on Twitter Share January 12, 2024 on Linkedin Email January 12, 2024 link
    • Notice to proceed is anticipated for mid-February.
    • Public Open House, January 31st from 3:00 p.m. - 7:00 p.m. - Hilton Garden Inn, Eagle. Stop by to learn more about the construction project in Eagle.
  • December 22, 2023

    Share December 22, 2023 on Facebook Share December 22, 2023 on Twitter Share December 22, 2023 on Linkedin Email December 22, 2023 link
    • Pre-Construction Meeting TBD.
    • Notice to Proceed is scheduled for January.
  • July 10, 2023

    Share July 10, 2023 on Facebook Share July 10, 2023 on Twitter Share July 10, 2023 on Linkedin Email July 10, 2023 link

    Construction of the Downtown Eagle Mobility Improvements: Eagle Road and State Street project has been split into two phases:

    Phase 1 – Scheduled To Start Construction Early 2024 And To Be Completed In The Fall Of 2024:

    • Eagle Road, SH-44 to the canal (just north of Plaza Drive) – Reconstructing the road with concrete and asphalt paving and replacing the sidewalk
      • This includes expanding the Eagle Road and Plaza Drive intersection with concrete pavement
        • 2 through lanes in each direction on Eagle Road
        • 2 left turns lanes to get from Plaza Drive to Eagle Road
      • Eagle Road will not be widened above the canal
    • Plaza Drive, Eagle Road to 2nd Street – Repave with asphalt pavement, replacing some sidewalk
    • State Street and 2nd Street intersection – Add a traffic signal and repave with asphalt pavement
      • Replacing some on-street parking on State Street with left turn lanes
    • Phase 1 map

    Phase 2 – Scheduled To Start Construction In Fall 2024 And To Be Completed In The Fall Of 2025:

    • Eagle Road, canal (just north of Plaza Drive) to State Street – Reconstructing the road with concrete pavement, replacing some sidewalk
      • Eagle Road will not be widened above the canal
    • State Street, Olde Park Place to 2nd Street – Reconstructing the roadway with concrete pavement, replacing/adding sidewalk and streetscaping
      • This includes reconfiguring and reconstructing the Eagle Road and State Street intersection
        • There will no longer be a left turn from eastbound State Street to southbound Eagle Road
          • Drivers will turn left at 2nd Street or Olde Park Place instead
    • Olde Park Place, State St to Aikens Street – Reconstruct and widen the road with asphalt pavement, adding on-street parking and 10-foot sidewalk on both sides
    • Aikens Street, Olde Park Place to Eagle Road – Reconstruct the road with asphalt pavement and add 5-foot sidewalk on the north side
    • Phase 2 map


    Images of Combined Phases

  • January-February 2021 Public Outreach

    Share January-February 2021 Public Outreach on Facebook Share January-February 2021 Public Outreach on Twitter Share January-February 2021 Public Outreach on Linkedin Email January-February 2021 Public Outreach link

    Find responses to frequently asked questions, and additional project information.

  • September 2020 Public Outreach

    Share September 2020 Public Outreach on Facebook Share September 2020 Public Outreach on Twitter Share September 2020 Public Outreach on Linkedin Email September 2020 Public Outreach link

    Learn more about the project and view the design elements here.

Page last updated: 22 Nov 2024, 09:10 AM