July 28, 2023

  • Grade work on east Ranch ongoing.
  • Concrete placements are scheduled for July 13th and 14th.
  • Asphalt paving was done on July 27th
  • N. Eagle Road closed July 18th for two weeks - set to re-open July 31st. Notification boards set. Demo has started. Pipework started in the intersection.
Share July 28, 2023 on Facebook Share July 28, 2023 on X (formerly Twitter) Share July 28, 2023 on Linkedin Email July 28, 2023 link

Project is substantially complete. 