Eagle Road and Ranch Drive Enhanced Pedestrian Crossing

Share Eagle Road and Ranch Drive Enhanced Pedestrian Crossing on Facebook Share Eagle Road and Ranch Drive Enhanced Pedestrian Crossing on Twitter Share Eagle Road and Ranch Drive Enhanced Pedestrian Crossing on Linkedin Email Eagle Road and Ranch Drive Enhanced Pedestrian Crossing link

Project is substantially complete. 

The Ada County Highway District (ACHD) will begin construction on the Eagle Road and Ranch Drive Enhanced Pedestrian Crossing project as early as the beginning of June 2023. The project is scheduled for substantial completion in September of 2023.*

Project Description:

  • Install a Pedestrian Hybrid Beacon (PHB) across Eagle Road at Ranch Drive
  • Reconstruct adjacent pedestrian ramps to meet modern standards
  • Remove and replace the existing asphalt pavement and stormwater pipes on Eagle Road at the intersection

*Due to high demand for contractors, labor and supplies, construction schedules may change.


The Ada County Highway District (ACHD) will begin construction on the Eagle Road and Ranch Drive Enhanced Pedestrian Crossing project as early as the beginning of June 2023. The project is scheduled for substantial completion in September of 2023.*

Project Description:

  • Install a Pedestrian Hybrid Beacon (PHB) across Eagle Road at Ranch Drive
  • Reconstruct adjacent pedestrian ramps to meet modern standards
  • Remove and replace the existing asphalt pavement and stormwater pipes on Eagle Road at the intersection

*Due to high demand for contractors, labor and supplies, construction schedules may change.


Project is substantially complete. 

  • August 4, 2023

    Share August 4, 2023 on Facebook Share August 4, 2023 on Twitter Share August 4, 2023 on Linkedin Email August 4, 2023 link
    • Project substantially complete.
  • July 28, 2023

    Share July 28, 2023 on Facebook Share July 28, 2023 on Twitter Share July 28, 2023 on Linkedin Email July 28, 2023 link
    • Grade work on east Ranch ongoing.
    • Concrete placements are scheduled for July 13th and 14th.
    • Asphalt paving was done on July 27th
    • N. Eagle Road closed July 18th for two weeks - set to re-open July 31st. Notification boards set. Demo has started. Pipework started in the intersection.
  • July 14, 2023

    Share July 14, 2023 on Facebook Share July 14, 2023 on Twitter Share July 14, 2023 on Linkedin Email July 14, 2023 link
    • Grade work on east Ranch ongoing
    • Concrete placements are scheduled for July 13th and 14th.
    • Eagle Road will be closed for a maximum of two weeks beginning July 17th.
  • July 13, 2023

    Share July 13, 2023 on Facebook Share July 13, 2023 on Twitter Share July 13, 2023 on Linkedin Email July 13, 2023 link

    Please review the detour map below for the Eagle & Ranch Project.

    Eagle Road at the intersection of Ranch will be closed starting Monday, July 17th and will be closed for approximately 2 weeks.

  • July 7, 2023

    Share July 7, 2023 on Facebook Share July 7, 2023 on Twitter Share July 7, 2023 on Linkedin Email July 7, 2023 link
    • Demo and concrete prep work ongoing.
    • Concrete placements are scheduled for July 6 & 7th.
    • Eagle Road will be closed for a maximum of two weeks, anticipated for July 17th thru July 31st.
  • June 30, 2023

    Share June 30, 2023 on Facebook Share June 30, 2023 on Twitter Share June 30, 2023 on Linkedin Email June 30, 2023 link
    • Work complete on the west side of Eagle and Ranch.
    • Contractor has moved to the east side and started demo.
    • Eagle Road will be closed for a maximum of two weeks, anticipated for July 17th thru July 31st.
  • June 27, 2023

    Share June 27, 2023 on Facebook Share June 27, 2023 on Twitter Share June 27, 2023 on Linkedin Email June 27, 2023 link
    • Please review the updated closure and detour route for the East side of Ranch Road.
  • June 23, 2023

    Share June 23, 2023 on Facebook Share June 23, 2023 on Twitter Share June 23, 2023 on Linkedin Email June 23, 2023 link
    • Work nearly complete on the west side of Eagle and Ranch.
    • Paving scheduled for June 23rd.
    • Contractor expects to start on the east side of Ranch on June 26th.
    • Eagle Road will be closed for a maximum of two weeks, anticipated for July 17th thru July 31st.
  • June 16, 2023

    Share June 16, 2023 on Facebook Share June 16, 2023 on Twitter Share June 16, 2023 on Linkedin Email June 16, 2023 link
    • Work started on the northwest side of Eagle and Ranch.
    • Eagle Road will be closed for a maximum of two weeks. Anticipated for July 17th thru July 31st.
    • Concrete demo started and preliminary survey is set.
  • June 2, 2023

    Share June 2, 2023 on Facebook Share June 2, 2023 on Twitter Share June 2, 2023 on Linkedin Email June 2, 2023 link
    • Starting Monday, June 5, work will begin on the project.

      During the first phase of work, Ranch Drive in Eagle will be closed to vehicles between Eagle Road and North Gray Pebble Way.

    • Pedestrian access will be restricted to one side during construction.
    • Eagle Road will remain open to northbound and southbound traffic, but there will be lane restrictions at the intersection at Ranch Drive.
    • Ranch Drive is expected to reopen west of Eagle Road at the end of June, when crews will shift work to the eastern side of Eagle Road.
    • However, lane restrictions on Eagle Road will be in place throughout the project.
    • In mid-July, Eagle Road will be closed at the intersection of Ranch Drive for about two weeks for road construction and the installation of a pedestrian hybrid beacon.