June 23, 2023

  • Work nearly complete on the west side of Eagle and Ranch.
  • Paving scheduled for June 23rd.
  • Contractor expects to start on the east side of Ranch on June 26th.
  • Eagle Road will be closed for a maximum of two weeks, anticipated for July 17th thru July 31st.
Share June 23, 2023 on Facebook Share June 23, 2023 on Twitter Share June 23, 2023 on Linkedin Email June 23, 2023 link

Project is substantially complete. 