April 11, 2025
- Lake Hazel and Eagle Intersection closed.
- Wall excavation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk anticipated starting April 21st.
Share April 11, 2025 on Facebook
Share April 11, 2025 on Twitter
Share April 11, 2025 on Linkedin
Email April 11, 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends