Eagle Road, Lake Hazel Road to Amity Road

Share Eagle Road, Lake Hazel Road to Amity Road on Facebook Share Eagle Road, Lake Hazel Road to Amity Road on Twitter Share Eagle Road, Lake Hazel Road to Amity Road on Linkedin Email Eagle Road, Lake Hazel Road to Amity Road link

The Ada County Highway District will be reconstructing Eagle Road between Lake Hazel and Amity. The purpose of this project is to improve traffic flow and increase safety for all users.

Roadway Description

  • Widen Eagle Road from Lake Hazel Road to Amity Road to two lanes in each direction with a center turn lane and center medians to calm traffic.
  • Construct a multi-lane roundabout at the intersection of Eagle Road and Taconic Drive.
  • Add a multi-use pathway on each side of Eagle Road and at the Lake Hazel intersection for bicyclists and pedestrians.

Eagle and Lake Hazel Intersection Description

  • Widen and signalize the Lake Hazel and Eagle intersection
  • Add dual left-turn lanes on most approaches
  • Include additional thru lanes
  • Add dedicated right turn lanes on two approaches
  • Install a multi-use pathway for bicyclists and pedestrians
  • Include painted crosswalks

The Ada County Highway District will be reconstructing Eagle Road between Lake Hazel and Amity. The purpose of this project is to improve traffic flow and increase safety for all users.

Roadway Description

  • Widen Eagle Road from Lake Hazel Road to Amity Road to two lanes in each direction with a center turn lane and center medians to calm traffic.
  • Construct a multi-lane roundabout at the intersection of Eagle Road and Taconic Drive.
  • Add a multi-use pathway on each side of Eagle Road and at the Lake Hazel intersection for bicyclists and pedestrians.

Eagle and Lake Hazel Intersection Description

  • Widen and signalize the Lake Hazel and Eagle intersection
  • Add dual left-turn lanes on most approaches
  • Include additional thru lanes
  • Add dedicated right turn lanes on two approaches
  • Install a multi-use pathway for bicyclists and pedestrians
  • Include painted crosswalks
  • August 1, 2025

    01 Aug 2025
    Share August 1, 2025 on Facebook Share August 1, 2025 on Twitter Share August 1, 2025 on Linkedin Email August 1, 2025 link

    Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction. Conduits and pole foundations ongoing. Concrete buffer being placed. Wall starting on northwest corner as early as August 4th.

    July 1st - Lake Hazel to Amity closed for duration of 2nd phase. Milling complete. Utilities relocating services. Removal ongoing. Excavation ongoing. Storm drain ongoing.

  • July 25, 2025

    25 Jul 2025
    Share July 25, 2025 on Facebook Share July 25, 2025 on Twitter Share July 25, 2025 on Linkedin Email July 25, 2025 link

    Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction. Conduits and pole foundations being placed. Concrete buffer being placed. Wall starting on northwest corner as early as July 28th.

    Lake Hazel to Amity closed for duration of 2nd phase - Milling complete. Utilities will be relocating services. Removal ongoing. Excavation ongoing. Underground work started July 21st.

  • July 18, 2025

    18 Jul 2025
    Share July 18, 2025 on Facebook Share July 18, 2025 on Twitter Share July 18, 2025 on Linkedin Email July 18, 2025 link

    Eagle and Lake Hazel Intersection

    • Lake Hazel and Eagle Intersection opened July 1st in the East/West direction
    • Conduits and pole foundations being placed
    • Concrete buffer being placed
    • Wall starting on northwest corner as early as July 28th

    Eagle, Lake Hazel to Amity

    • Lake Hazel to Amity closed for duration of 2nd phase
    • Milling complete
    • Utilities will be relocating services.
    • Removal ongoing
    • Excavation ongoing
    • Underground work starting July 21st
  • July 11, 2025

    11 Jul 2025
    Share July 11, 2025 on Facebook Share July 11, 2025 on Twitter Share July 11, 2025 on Linkedin Email July 11, 2025 link

    Eagle and Lake Hazel Intersection

    • Lake Hazel and Eagle intersection opening July 1st in the East/West direction.
    • Conduits and pole foundations being placed.
    • Concrete buffer being placed.
    • Concrete paving completed until sound wall installed

    Lake Hazel to Amity closed for duration of 2nd phase - Milling complete. Utilities will be relocating services. Removal ongoing.


  • July 2, 2025

    02 Jul 2025
    Share July 2, 2025 on Facebook Share July 2, 2025 on Twitter Share July 2, 2025 on Linkedin Email July 2, 2025 link

    Phase 1 – Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opening July 1st in the East/West direction. Conduits and pole foundations being placed. Concrete buffer being placed. Concrete paving completed until wall installed.

    Phase 2 started July 1st - Lake Hazel to Amity closed for duration of 2nd phase. Milling scheduled for July 1st – 3rd. Utilities will be relocating services.

  • Phase 2 Begins Tuesday, July 1

    27 Jun 2025
    Share Phase 2 Begins Tuesday, July 1 on Facebook Share Phase 2 Begins Tuesday, July 1 on Twitter Share Phase 2 Begins Tuesday, July 1 on Linkedin Email Phase 2 Begins Tuesday, July 1 link

    Phase 2 of the Eagle Road, Lake Hazel to Amity Road project will begin next week.

    Starting Tuesday, July 1, Lake Hazel Road will be open to east-west traffic. Also beginning Tuesday, Eagle Road will be fully closed between Lake Hazel and Amity Roads.

    Local access will be maintained during the construction. Temporary stop signs and speed bumps will be installed in several neighborhood intersections near the road closure. Non-local traffic should use Cloverdale to the east, and Locust Grove to the west to get around the closure. (see detour map)

    The roadwork is part of ACHD’s Eagle Road, Lake Hazel to Amity Road project, which includes widening and signalizing the intersection of Eagle and Lake Hazel, a multi-lane roundabout at Eagle and Taconic, widening Eagle Road, and adding a multi-use pathway for bicyclists and pedestrians. The entire project is expected to be complete in November 2025.

  • June 26, 2025

    26 Jun 2025
    Share June 26, 2025 on Facebook Share June 26, 2025 on Twitter Share June 26, 2025 on Linkedin Email June 26, 2025 link
    • Phase 1 – Eagle and Lake Hazel Intersection.
    • Lake Hazel and Eagle Intersection opening July 1st in the East/West Direction.
    • Conduits and pole foundations being placed. Concrete buffer being placed. Concrete paving completed until soundwall installed. Paving ongoing until June 30th.
    • Phase 2 anticipated starting July 1st. Lake Hazel to Amity closed for duration of 2nd phase. Milling Starting July 1st – 3rd. Utilities will be relocating services.
  • June 20, 2025

    21 Jun 2025
    Share June 20, 2025 on Facebook Share June 20, 2025 on Twitter Share June 20, 2025 on Linkedin Email June 20, 2025 link
    • Lake Hazel and Eagle Intersection closed
    • Wall A and other miscellaneous walls ongoing
    • Conduits and pole foundations being placed
    • Placing road base
    • Sidewalk being placed
    • Concrete Paving completed until Soundwall installed
    • Preparing road for asphalt
    • Paving anticipated June 26th
    • Phase 2 Anticipated starting first week of July
      • Lake Hazel to Amity closed for duration of 2nd phase
      • Lake Hazel & Eagle Intersection will be open in the East/West direction.
  • June 13, 2025

    13 Jun 2025
    Share June 13, 2025 on Facebook Share June 13, 2025 on Twitter Share June 13, 2025 on Linkedin Email June 13, 2025 link
    • Lake Hazel and Eagle Intersection closed.
    • Wall installation ongoing.
    • Conduits and pole foundations being placed.
    • Placing road base.
    • Sidewalk being placed.
    • Concrete paving started June 2nd and will be on-going through June 18th.
    • South and West legs complete.
  • June 6, 2025

    06 Jun 2025
    Share June 6, 2025 on Facebook Share June 6, 2025 on Twitter Share June 6, 2025 on Linkedin Email June 6, 2025 link
    • Lake Hazel and Eagle Intersection closed.
    • Wall installation ongoing.
    • Conduits and pole foundations being placed.
    • Placing road base.
    • Sidewalk being placed.
    • Concrete paving June 2nd and will be on-going through June 18th.
Page last updated: 01 Aug 2025, 12:04 PM