August 29, 2025

  • Lake Hazel and Eagle Intersection opened July 1st - east and west.
  • Conduits and pole foundations placed August 12th.
  • Concrete buffer ongoing.
  • Wall starting on northwest corner in early September.
  • Lake Hazel to Amity closed for duration of 2nd phase.
  • Utilities relocating services.
  • Excavation ongoing.
  • Storm drain ongoing.
  • Sidewalk ongoing between Taconic and Lake Hazel.
  • Working on Taconic intersection.