December 4, 2025

Eagle and Lake Hazel Intersection

  • Lake Hazel and Eagle Intersection opened July 1st in the east/west direction
  • Concrete fence complete
  • Concrete Intersection placed: Signage and Pavement markings being placed. Preparing for placement of signal poles. Anticipated December 17th. Finishing asphalt paving between Lake Hazel and Levine week of November 24th.

Lake Hazel to Amity

  • Lake Hazel to Amity closed for duration.
  • Working on Taconic intersection.
  • Placed concrete paving at all approaches of roundabout.
  • Anticipated paving between Taconic and Amity week of November 10th.
  • Taconic Intersection concrete placement starting November 19th – December 12th.