July 11, 2025

Eagle and Lake Hazel Intersection

  • Lake Hazel and Eagle intersection opening July 1st in the East/West direction.
  • Conduits and pole foundations being placed.
  • Concrete buffer being placed.
  • Concrete paving completed until sound wall installed

Lake Hazel to Amity closed for duration of 2nd phase - Milling complete. Utilities will be relocating services. Removal ongoing.