July 18, 2025

Eagle and Lake Hazel Intersection

  • Lake Hazel and Eagle Intersection opened July 1st in the East/West direction
  • Conduits and pole foundations being placed
  • Concrete buffer being placed
  • Wall starting on northwest corner as early as July 28th

Eagle, Lake Hazel to Amity

  • Lake Hazel to Amity closed for duration of 2nd phase
  • Milling complete
  • Utilities will be relocating services.
  • Removal ongoing
  • Excavation ongoing
  • Underground work starting July 21st
Share July 18, 2025 on Facebook Share July 18, 2025 on Twitter Share July 18, 2025 on Linkedin Email July 18, 2025 link