July 18, 2025
Eagle and Lake Hazel Intersection
- Lake Hazel and Eagle Intersection opened July 1st in the East/West direction
- Conduits and pole foundations being placed
- Concrete buffer being placed
- Wall starting on northwest corner as early as July 28th
Eagle, Lake Hazel to Amity
- Lake Hazel to Amity closed for duration of 2nd phase
- Milling complete
- Utilities will be relocating services.
- Removal ongoing
- Excavation ongoing
- Underground work starting July 21st