July 2, 2025

Phase 1 – Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opening July 1st in the East/West direction. Conduits and pole foundations being placed. Concrete buffer being placed. Concrete paving completed until wall installed.

Phase 2 started July 1st - Lake Hazel to Amity closed for duration of 2nd phase. Milling scheduled for July 1st – 3rd. Utilities will be relocating services.