June 20, 2025
- Lake Hazel and Eagle Intersection closed
- Wall A and other miscellaneous walls ongoing
- Conduits and pole foundations being placed
- Placing road base
- Sidewalk being placed
- Concrete Paving completed until Soundwall installed
- Preparing road for asphalt
- Paving anticipated June 26th
- Phase 2 Anticipated starting first week of July
- Lake Hazel to Amity closed for duration of 2nd phase
- Lake Hazel & Eagle Intersection will be open in the East/West direction.