  • Phase 1 – Eagle and Lake Hazel Intersection.
  • Lake Hazel and Eagle Intersection opening July 1st in the East/West Direction.
  • Conduits and pole foundations being placed. Concrete buffer being placed. Concrete paving completed until soundwall installed. Paving ongoing until June 30th.
  • Phase 2 anticipated starting July 1st. Lake Hazel to Amity closed for duration of 2nd phase. Milling Starting July 1st – 3rd. Utilities will be relocating services.