November 20, 2025
- Eagle and Lake Hazel Intersection o Lake Hazel and Eagle Intersection opened July 1st in the east/west direction.
- Concrete fence complete.
- Concrete Intersection being placed: November 21st starting at 2am. November 24th starting at 3 am.
- Prepping for placement of signal poles. Anticipated December 3rd. Finishing asphalt paving between Lake Hazel and Levine week of November 24th.Lake Hazel to Amity.
- Lake Hazel to Amity closed for duration.
- Working on Taconic intersection.
- Placed concrete paving at all approaches of roundabout o Anticipated paving between Taconic and Amity week of November 10th.
- Taconic Intersection concrete placement starting November 19th.