Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction. Concrete fence being placed. Finishing up concrete. Prepping for placement of Signal poles.

Lake Hazel to Amity - Lake Hazel to Amity closed for duration. Sidewalk & curb ongoing between Taconic and Amity. Working on Taconic intersection. Placed concrete paving at all approaches of roundabout. Anticipated paving between Taconic and Amity week of November 10th .