October 17, 2024

17 Oct 2024

Lake Hazel and Eagle Intersection closed

  • Cut and fill ongoing at Lake Hazel intersection.
  • Retaining wall construction started October 16th.
  • Idaho Power relocating poles.
  • Communication utilities will relocate after poles.