November 13, 2026


  • Working on the permanent crossing.
  • Veolia is working on water across Boise River bridge.
  • Dewatering installation is ongoing.
  • Removal of bridge after dewatering setup.
Intermountain Gas has completed the temporary relocation work. The company is continuing to monitor the temporary facilities to ensure service remains safe, reliable, and functioning as normal.

Permanent relocation work by Intermountain Gas is on-going.