October 21, 2022

  • Veolia completed relocation.
  • SW corner being prepped for concrete.
  • night work on 24th for medium curb.
Share October 21, 2022 on Facebook Share October 21, 2022 on Twitter Share October 21, 2022 on Linkedin Email October 21, 2022 link

This project is substantially complete.