May 8, 2025

  • Floating Feather Road is closed.
  • Culvert complete.
  • Floating Feather Rd - Sewer line ongoing. Storm Drain complete. Contractor excavating and prepping for curb/sidewalk. Sidewalk & curb ongoing. Paving anticipated May 20th.