May 8, 2025

08 May 2025
  • Floating Feather Road is closed.
  • Culvert complete.
  • Floating Feather Rd - Sewer line ongoing. Storm Drain complete. Contractor excavating and prepping for curb/sidewalk. Sidewalk & curb ongoing. Paving anticipated May 20th.
Share May 8, 2025 on Facebook Share May 8, 2025 on Twitter Share May 8, 2025 on Linkedin Email May 8, 2025 link
#<Object:0x00007f805442f168>