Floating Feather Bridge & Sidewalk Project

Share Floating Feather Bridge & Sidewalk Project on Facebook Share Floating Feather Bridge & Sidewalk Project on Twitter Share Floating Feather Bridge & Sidewalk Project on Linkedin Email Floating Feather Bridge & Sidewalk Project link

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Floating Feather Road, east of Munger Road, starting as early as mid-October 2024.* Construction is expected to be complete in the spring of 2025.

Project Overview

  • Remove and replace the existing bridge over the Middleton Canal.
  • Add multi-use pathways and sidewalk on both sides of Floating Feather Road to fill existing pedestrian gaps and improve connectivity.
  • Upgrade stormwater facilities to improve drainage.
  • Reconstruct the roadway.

Construction Impacts

  • Floating Feather Road will be closed during construction
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with homeowners to minimize construction impacts

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Floating Feather Road, east of Munger Road, starting as early as mid-October 2024.* Construction is expected to be complete in the spring of 2025.

Project Overview

  • Remove and replace the existing bridge over the Middleton Canal.
  • Add multi-use pathways and sidewalk on both sides of Floating Feather Road to fill existing pedestrian gaps and improve connectivity.
  • Upgrade stormwater facilities to improve drainage.
  • Reconstruct the roadway.

Construction Impacts

  • Floating Feather Road will be closed during construction
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with homeowners to minimize construction impacts
  • February 28, 2025

    Share February 28, 2025 on Facebook Share February 28, 2025 on Twitter Share February 28, 2025 on Linkedin Email February 28, 2025 link
    • Floating Feather Road is closed.
    • Culvert placed.
    • Grouting and placing waterproof membrane.
    • Working on wingwalls.
    • Sewer installation on Floating Feather anticipated starting March 10th.
  • February 20, 2025

    Share February 20, 2025 on Facebook Share February 20, 2025 on Twitter Share February 20, 2025 on Linkedin Email February 20, 2025 link
    • Floating Feather Road is closed.
    • Bridge footings placed.
    • Star waterline ongoing.
    • Culvert placed.
    • Working on wingwalls.
  • February 14, 2025

    Share February 14, 2025 on Facebook Share February 14, 2025 on Twitter Share February 14, 2025 on Linkedin Email February 14, 2025 link
    • Floating Feather Road is closed.
    • Bridge footings placed.
    • Star waterline ongoing.
    • Setting box culvert February 18th.
  • February 7, 2025

    Share February 7, 2025 on Facebook Share February 7, 2025 on Twitter Share February 7, 2025 on Linkedin Email February 7, 2025 link
    • Floating Feather Road is closed.
    • Bridge footings placed.
    • Star waterline ongoing.
    • Setting box culvert February 12th.
  • January 31, 2025

    Share January 31, 2025 on Facebook Share January 31, 2025 on Twitter Share January 31, 2025 on Linkedin Email January 31, 2025 link
    • Floating Feather Road is closed.
    • Contractor setting up dewatering.
    • Excavating for bridge footings.
    • Star water line being relocated.
    • Prepping for footings started January 20th.
    • Footings being placed Feb 3rd.
  • January 23, 2025

    Share January 23, 2025 on Facebook Share January 23, 2025 on Twitter Share January 23, 2025 on Linkedin Email January 23, 2025 link
    • Floating Feather Road is closed.
    • Contractor setting up dewatering.
    • Excavating for bridge footings.
    • Star water line being relocated.
    • Prepping for footings started January 20th.
  • January 17, 2025

    Share January 17, 2025 on Facebook Share January 17, 2025 on Twitter Share January 17, 2025 on Linkedin Email January 17, 2025 link
    • Floating Feather Road is closed.
    • Contractor setting up dewatering.
    • Excavating for bridge footings.
    • Star water line being relocated.
    • Prepping for footings starting January 20th.
  • January 10, 2024

    Share January 10, 2024 on Facebook Share January 10, 2024 on Twitter Share January 10, 2024 on Linkedin Email January 10, 2024 link
    • Floating Feather Road is closed.
    • Contractor setting up dewatering.
    • Excavating for bridge footings.
    • Star water line being relocated.
  • January 3, 2025

    Share January 3, 2025 on Facebook Share January 3, 2025 on Twitter Share January 3, 2025 on Linkedin Email January 3, 2025 link
    • Floating Feather Road is closed.
    • Contractor setting up dewatering.
    • Removal of bridge started December 9th.
    • Excavating for bridge footings.
  • December 20, 2024

    Share December 20, 2024 on Facebook Share December 20, 2024 on Twitter Share December 20, 2024 on Linkedin Email December 20, 2024 link
    • Floating Feather Road is closed.
    • Contractor setting up dewatering.
    • Removal of bridge started December 9th.
    • Excavating for bridge foorings.
Page last updated: 28 Feb 2025, 12:47 PM