Gary Lane and Elm Brook Drive Enhanced Pedestrian Crossing

Share Gary Lane and Elm Brook Drive Enhanced Pedestrian Crossing on Facebook Share Gary Lane and Elm Brook Drive Enhanced Pedestrian Crossing on Twitter Share Gary Lane and Elm Brook Drive Enhanced Pedestrian Crossing on Linkedin Email Gary Lane and Elm Brook Drive Enhanced Pedestrian Crossing link

This project is substantially complete

Starting as early as June, the Ada County Highway District (ACHD) will start construction on the Gary Lane and Elm Brook Drive Enhanced Pedestrian Crossing. The purpose of this project is to improve safety near Riverglen Junior High School. Construction is expected to be completed in early August of 2024.*

Project Description

  • Install a rectangular rapid flashing beacon (RRFB) across Gary Lane at Elm Brook Drive
  • Add bulb-outs on Elm Brook Drive to improve safety
  • Reconstruct adjacent pedestrian ramps to meet modern standards

*Due to high demand for contractors, labor and supplies, the construction schedules may change.

Construction Impacts

  • Temporary road closures
  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts

Starting as early as June, the Ada County Highway District (ACHD) will start construction on the Gary Lane and Elm Brook Drive Enhanced Pedestrian Crossing. The purpose of this project is to improve safety near Riverglen Junior High School. Construction is expected to be completed in early August of 2024.*

Project Description

  • Install a rectangular rapid flashing beacon (RRFB) across Gary Lane at Elm Brook Drive
  • Add bulb-outs on Elm Brook Drive to improve safety
  • Reconstruct adjacent pedestrian ramps to meet modern standards

*Due to high demand for contractors, labor and supplies, the construction schedules may change.

Construction Impacts

  • Temporary road closures
  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts

This project is substantially complete

  • August 9, 2024

    Share August 9, 2024 on Facebook Share August 9, 2024 on Twitter Share August 9, 2024 on Linkedin Email August 9, 2024 link
    • RRFB signal was activated on August 8th.
    • Remaining work includes landscape repair.
  • August 2, 2024

    Share August 2, 2024 on Facebook Share August 2, 2024 on Twitter Share August 2, 2024 on Linkedin Email August 2, 2024 link
    • Concrete work is complete.
    • Asphalt paving was completed August 1st.
    • Remaining work includes permanent pavement markings, signage, and RRFB activation.
  • July 26, 2024

    Share July 26, 2024 on Facebook Share July 26, 2024 on Twitter Share July 26, 2024 on Linkedin Email July 26, 2024 link
    • Concrete work is nearly complete.
  • June 28, 2024

    Share June 28, 2024 on Facebook Share June 28, 2024 on Twitter Share June 28, 2024 on Linkedin Email June 28, 2024 link
    • Contractor started work on June 26th.