Hanley Place Bridge Project

Share Hanley Place Bridge Project on Facebook Share Hanley Place Bridge Project on Twitter Share Hanley Place Bridge Project on Linkedin Email Hanley Place Bridge Project link

This project is substantially complete

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Hanley Place, north of Chaparral Road, as early as the beginning of May or possibly as late as June 2023. Construction is expected to be complete fall of 2023.*

This bridge improvement project will include removing and replacing the existing bridge over Willow Creek.

*Due to high demand for contractors, labor and supplies, construction schedules may change.

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Hanley Place, north of Chaparral Road, as early as the beginning of May or possibly as late as June 2023. Construction is expected to be complete fall of 2023.*

This bridge improvement project will include removing and replacing the existing bridge over Willow Creek.

*Due to high demand for contractors, labor and supplies, construction schedules may change.

This project is substantially complete

  • October 12, 2023

    Share October 12, 2023 on Facebook Share October 12, 2023 on Twitter Share October 12, 2023 on Linkedin Email October 12, 2023 link

    This project is substantially complete.

  • September 8, 2023

    Share September 8, 2023 on Facebook Share September 8, 2023 on Twitter Share September 8, 2023 on Linkedin Email September 8, 2023 link
    • Paving Complete
    • Guardrail being placed week of September 4th
    • Riprap on East side ongoing
  • August 31, 2023

    Share August 31, 2023 on Facebook Share August 31, 2023 on Twitter Share August 31, 2023 on Linkedin Email August 31, 2023 link
    • Paving complete
    • Guard rail being laced week of September 4th.
  • August 25, 2023

    Share August 25, 2023 on Facebook Share August 25, 2023 on Twitter Share August 25, 2023 on Linkedin Email August 25, 2023 link
    • Placing waterproof membrane August 23rd.
    • Paving anticipated week of August 28th.
    • Placing fill for new approaches.
  • August 18, 2023

    Share August 18, 2023 on Facebook Share August 18, 2023 on Twitter Share August 18, 2023 on Linkedin Email August 18, 2023 link
    • Placing waterproof membrane August 16th.
    • Paving anticipated the week of August 21st.
    • Placing fill for new approaches.
  • August 11, 2023

    Share August 11, 2023 on Facebook Share August 11, 2023 on Twitter Share August 11, 2023 on Linkedin Email August 11, 2023 link
    • Curb on deck being placed.
    • Place backfill behind abutment.
    • Placing fill for new approaches.
  • August 4, 2023

    Share August 4, 2023 on Facebook Share August 4, 2023 on Twitter Share August 4, 2023 on Linkedin Email August 4, 2023 link
    • Excavating and shaping between abutments.
    • Voided slabs starting were set July 27th.
    • Closure pour for voided slab ongoing.
    • Place backfill behind abutment.

    Interested in reviewing the progress of the project? Click the drone footage here.

  • July 28, 2023

    Share July 28, 2023 on Facebook Share July 28, 2023 on Twitter Share July 28, 2023 on Linkedin Email July 28, 2023 link
    • Excavating and shaping between abutments
    • Voided Slabs starting were set on July 24th.
  • July 21, 2023

    Share July 21, 2023 on Facebook Share July 21, 2023 on Twitter Share July 21, 2023 on Linkedin Email July 21, 2023 link
    • Excavating and shaping between abutments.
    • Voided slabs starting to be made at precast yard July 12th.
    • Anticipated placement of voided slabs July 27th.
  • July 14, 2023

    Share July 14, 2023 on Facebook Share July 14, 2023 on Twitter Share July 14, 2023 on Linkedin Email July 14, 2023 link
    • Excavating and shaping between abutments
    • Voided slabs starting to be made at precast yard July 12th - anticipated placement of voided slabs July 27th.