  • Excavating and shaping between abutments.
  • Voided slabs starting were set July 27th.
  • Closure pour for voided slab ongoing.
  • Place backfill behind abutment.

Interested in reviewing the progress of the project? Click the drone footage here.(External link)

Share August 4, 2023 on Facebook Share August 4, 2023 on Twitter Share August 4, 2023 on Linkedin Email August 4, 2023 link

This project is substantially complete