August 4, 2023
- Excavating and shaping between abutments.
- Voided slabs starting were set July 27th.
- Closure pour for voided slab ongoing.
- Place backfill behind abutment.
Interested in reviewing the progress of the project? Click the drone footage here.
Share August 4, 2023 on Facebook
Share August 4, 2023 on Twitter
Share August 4, 2023 on Linkedin
Email August 4, 2023 link
This project is substantially complete