When will construction happen?

    Construction is scheduled to begin as early as mid-August and be completed by October 2025.
    Note: Construction schedules may change due to high demand for contractors, labor, and supplies.

    Why was this timeframe selected?

    The construction window was chosen to ensure the bridge is open by mid October to support maintenance access for the Boise Project Board of Control.(External link) The bridge is a critical route for their operations. 

    After the irrigation season ends, crews will complete additional work underneath the bridge, but it will remain open during that time.


     

    Is this an emergency closure?

    No. This is planned, routine maintenance as part of ACHD’s Bridge Preventative Maintenance Program. The work is intended to extend the life of the structure and keep the bridge safe and reliable.