Boise Avenue Bridge
As part of the Ada County Highway District’s (ACHD) Bridge Preventative Maintenance Program, ACHD will perform routine maintenance on the Boise Avenue bridge (formerly Healey Road) over the New York Canal.
This planned work includes preventative deck maintenance to extend the life of the structure and ensure it remains safe and reliable. The improvements will help maintain a smooth, durable driving surface for all users.
Construction Impacts
- Lane restrictions
- General construction noise, dust, equipment backup alarms, and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
Construction schedules may change due to high demand for contractors, labor, and supplies.
As part of the Ada County Highway District’s (ACHD) Bridge Preventative Maintenance Program, ACHD will perform routine maintenance on the Boise Avenue bridge (formerly Healey Road) over the New York Canal.
This planned work includes preventative deck maintenance to extend the life of the structure and ensure it remains safe and reliable. The improvements will help maintain a smooth, durable driving surface for all users.
Construction Impacts
- Lane restrictions
- General construction noise, dust, equipment backup alarms, and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
Construction schedules may change due to high demand for contractors, labor, and supplies.
-
April 2, 2026
Share April 2, 2026 on Facebook Share April 2, 2026 on Twitter Share April 2, 2026 on Linkedin Email April 2, 2026 link- Substructure repairs are complete.
- Deck work started March 16th.
- Half the bridge will be done at a time.
- The road will remain open to one lane with a temporary signal.
- Concrete for the first half was placed on March 27th.
- Substructure repairs are complete.
- Deck work started March 16th.
- Half the bridge will be done at a time.
- The road will remain open to one lane with a temporary signal.
- Concrete for the first half was placed on March 27th.
-
March 26, 2026
Share March 26, 2026 on Facebook Share March 26, 2026 on Twitter Share March 26, 2026 on Linkedin Email March 26, 2026 link- Substructure repairs are complete.
- Deck work started March 16th.
- Half the bridge will be done at a time.
- The road will remain open to one lane with a temporary signal.
- Concrete for the first half was placed on March 27th.
- Substructure repairs are complete.
- Deck work started March 16th.
- Half the bridge will be done at a time.
- The road will remain open to one lane with a temporary signal.
- Concrete for the first half was placed on March 27th.
-
March 19, 2026
Share March 19, 2026 on Facebook Share March 19, 2026 on Twitter Share March 19, 2026 on Linkedin Email March 19, 2026 link- Substructure repairs are complete.
- Deck work started March 16th. Half the bridge will be done at a time.
- The road will remain open to one lane with a temporary signal.
- Substructure repairs are complete.
- Deck work started March 16th. Half the bridge will be done at a time.
- The road will remain open to one lane with a temporary signal.
-
March 13, 2026
Share March 13, 2026 on Facebook Share March 13, 2026 on Twitter Share March 13, 2026 on Linkedin Email March 13, 2026 link- Contractor working on substructure repairs, nearly complete.
- Deck work anticipated to start March 16th. Half the bridge will be done at a time. The road will remain open to one lane with a temporary signal.
- Contractor working on substructure repairs, nearly complete.
- Deck work anticipated to start March 16th. Half the bridge will be done at a time. The road will remain open to one lane with a temporary signal.
-
March 6, 2026
Share March 6, 2026 on Facebook Share March 6, 2026 on Twitter Share March 6, 2026 on Linkedin Email March 6, 2026 link- Contractor working on substructure repairs.
- Deck work anticipated to start March 16th.
- Half the bridge will be done at a time. The road will remain open to one lane with a temporary signal.
- Contractor working on substructure repairs.
- Deck work anticipated to start March 16th.
- Half the bridge will be done at a time. The road will remain open to one lane with a temporary signal.
-
February 27, 2026
Share February 27, 2026 on Facebook Share February 27, 2026 on Twitter Share February 27, 2026 on Linkedin Email February 27, 2026 link- Contractor working on substructure repairs.
- Deck work anticipated to start in late March.
- Contractor working on substructure repairs.
- Deck work anticipated to start in late March.
-
February 19, 2026
Share February 19, 2026 on Facebook Share February 19, 2026 on Twitter Share February 19, 2026 on Linkedin Email February 19, 2026 link- Contractor working on substructure repairs.
- Contractor working on substructure repairs.
-
Construction Starts This Week - February 11, 2026
Share Construction Starts This Week - February 11, 2026 on Facebook Share Construction Starts This Week - February 11, 2026 on Twitter Share Construction Starts This Week - February 11, 2026 on Linkedin Email Construction Starts This Week - February 11, 2026 linkWork begins this week on the Boise Avenue Bridge (formerly Healey Road).
During the first phase of the project, crews will primarily work underneath the bridge. Some equipment will be staged on the bridge during daytime work hours, which will require a lane closure.
While crews are working, a temporary signal will direct traffic across the bridge. Outside of working hours, the signal will be placed in flash mode and all lanes will reopen to traffic.
Delays are expected to be minimal through this phase of work, but drivers should use caution in the area and allow extra space for crews to work.
Crews will work daily, including weekends, to complete the necessary work beneath the bridge before mid-March.
Work on this project is expected to be completed later this spring.
Work begins this week on the Boise Avenue Bridge (formerly Healey Road).
During the first phase of the project, crews will primarily work underneath the bridge. Some equipment will be staged on the bridge during daytime work hours, which will require a lane closure.
While crews are working, a temporary signal will direct traffic across the bridge. Outside of working hours, the signal will be placed in flash mode and all lanes will reopen to traffic.
Delays are expected to be minimal through this phase of work, but drivers should use caution in the area and allow extra space for crews to work.
Crews will work daily, including weekends, to complete the necessary work beneath the bridge before mid-March.
Work on this project is expected to be completed later this spring.
-
February 5, 2025
Share February 5, 2025 on Facebook Share February 5, 2025 on Twitter Share February 5, 2025 on Linkedin Email February 5, 2025 linkNotice to proceed starts on February 9th.
Notice to proceed starts on February 9th.
-
Boise Avenue Bridge Construction Starts Soon
Share Boise Avenue Bridge Construction Starts Soon on Facebook Share Boise Avenue Bridge Construction Starts Soon on Twitter Share Boise Avenue Bridge Construction Starts Soon on Linkedin Email Boise Avenue Bridge Construction Starts Soon linkAs part of the Ada County Highway District’s (ACHD) Bridge Preventative Maintenance Program, ACHD will perform routine maintenance on the Boise Avenue Bridge (formerly Healey Road) over the New York Canal, starting as early as February 2026.
This planned work includes preventative deck maintenance to extend the life of the structure and ensure it remains safe and reliable. The improvements will help maintain a smooth, durable driving surface for all users.
As part of the Ada County Highway District’s (ACHD) Bridge Preventative Maintenance Program, ACHD will perform routine maintenance on the Boise Avenue Bridge (formerly Healey Road) over the New York Canal, starting as early as February 2026.
This planned work includes preventative deck maintenance to extend the life of the structure and ensure it remains safe and reliable. The improvements will help maintain a smooth, durable driving surface for all users.
Contact Us
Who's Listening
-
Supervisor, Construction
Phone 208-387-6100 Email connect@achdidaho.org -
Project Manager
Phone 208387-6100 Email connect@achdidaho.org