April 16, 2026

  • Substructure repairs are complete.
  • Deck work started March 16th.
  • Half the bridge will be done at a time.
  • The road will remain open to one lane with a temporary signal.
  • Traffic was swapped on April 9th and work began on the second half of the bridge.
Share April 16, 2026 on Facebook Share April 16, 2026 on X (formerly Twitter) Share April 16, 2026 on Linkedin Email April 16, 2026 link

This project is substantially complete