May 13, 2026

  • Substructure repairs are complete.
  • Deck work is complete. The roadway will open no later than May 15th, after concrete reaches minimum strength.
  • An epoxy overlay will be placed after the new concrete has cured for a minimum of 28 days.
Share May 13, 2026 on Facebook Share May 13, 2026 on Twitter Share May 13, 2026 on Linkedin Email May 13, 2026 link

This project is substantially complete