May 21, 2026

  • Boise Ave (Healey Bridge) #2149 – work began February 9th.
  • Substructure repairs are complete.
  • Deck work is complete. The roadway will open no later than May 15th, after concrete reaches minimum strength.
  • An epoxy overlay will be placed after the new concrete has cured for a minimum of 28 days.
Share May 21, 2026 on Facebook Share May 21, 2026 on Twitter Share May 21, 2026 on Linkedin Email May 21, 2026 link

This project is substantially complete