May 21, 2026

  • Boise Ave (Healey Bridge) #2149 – work began February 9th.
  • Substructure repairs are complete.
  • Deck work is complete. The roadway will open no later than May 15th, after concrete reaches minimum strength.
  • An epoxy overlay will be placed after the new concrete has cured for a minimum of 28 days.