May 8, 2026
- Boise Ave (Healey Bridge) #2149 – work began February 9th.
- Substructure repairs are complete.
- Deck work is complete.
- The roadway will open no later than May 15th, after concrete reaches minimum strength.
- An epoxy overlay will be placed after the new concrete has cured for a minimum of 28 days.