April 10, 2026

  • Hubbard Road remains closed between Ten Mile Road and Linder Road.
  • Roadway has been milled, and demo of existing facilities is complete.
  • Contractor continued roadway import and grade prep at Ten Mile headed east to Linder.
  • Contractor completed the City of Kuna utility work, up to Linder.
  • Contactor has completed the retaining wall on the northwest end of the project.
  • Irrigation work is complete.
  • Contractor has started working on concrete sidewalk, curb, and gutter placements at various locations along Hubbard.
  • Paving is scheduled for the end of the month, for phase 1.